CTDOT 0134-0147 Modern Roundabout at RTE 190 & RTE 319

Project Description

Location: Stafford CT
Project Completed: Fall 2021
Service: Modern Roundabout

The Project

Spazzarini Construction was awarded the $3,662,918.05 contract for the installation of a modern roundabout located at the intersection of RTE 190 and RTE 319 in Stafford CT. This multi phased project consists of the installation of 172 LF of 16’x8’ box culverts supplied by CSI Concrete Systems, 1000 CY of Pervious Structure Backfill, 4500 CY of Process Aggregate Base, 4600 Tons of PMA Asphalt supplied and installed by Palmer Paving Corporation, and 7000 SF of Stamped concrete installed by J&P Construction. This project started in Spring 2020 and was completed in the Fall of 2021.